Review pack M3
Command: fra review-pack --milestone M3
Review pack: M3 First GaN half-bridge samples tested
DRAFT generated by fra. FICTIONAL example data. Sources in brackets.
- Work package: WP3 GaN power module and gate driver (lead Partner C) [WorkPackages!4]
- Planned date: 2026-02-06; status: delayed; evidence: none recorded [Milestones!4]
- Data as of 2026-07-10
Agenda
- Opening, attendance, approval of the minutes of MR-07 [minutes/2026-07-03_MR-07.md:1]
- WP3 status against the M3 criteria (WP lead)
- Evidence review: evidence still to be provided
- Open points (0 data findings, 1 open linked actions)
- Risks of WP3
- Decision on M3: passed / passed with conditions / not passed
- New actions, next meeting
Open points
- A-026 (in progress, owner Lead WP3 (Partner C), due 2026-08-10): Agree recovery plan for M3 [ActionItems!26]
- Risk R-03: Switching losses higher than expected (P4 x I4), mitigation: Plan an extra layout iteration in the schedule [Risks!4]
Earlier discussion in minutes
- M3 reviewed in MR-05 (2026-03-28) [minutes/2026-03-28_MR-05.md:1]
- D-04-2 (MR-04, 2026-01-25): Switching frequency target is 40 kHz [minutes/2026-01-25_MR-04.md:24]
- D-06-1 (MR-06, 2026-05-27): A second GaN sample supplier is qualified [minutes/2026-05-27_MR-06.md:23]
Action log extract
| Action | WP | Milestone | Description | Owner | Due | Status | Last update | Source |
|---|---|---|---|---|---|---|---|---|
| A-026 | WP3 | M3 | Agree recovery plan for M3 | Lead WP3 (Partner C) | 2026-08-10 | in progress | 2026-07-01 | ActionItems!26 |
| A-006 | WP3 | M2 | Check dV/dt limits against the motor insulation spec | Lead WP3 (Partner C) | 2026-08-12 | open | 2025-11-21 | ActionItems!7 |
| A-016 | WP3 | - | Run the double-pulse test campaign | Lead WP3 (Partner C) | 2026-07-16 | in progress | 2026-07-09 | ActionItems!16 |