Progress report (deterministic)

Also produced as .docx. Command: fra report --period 2026-H1

Progress report 2026-H1: eDrive-X (FICTIONAL example project)

DRAFT generated by fra from the tracker and minutes. FICTIONAL example data. Every paragraph and table row names its source (sheet!row or minutes file:line).

Reporting period 2026-01-01 to 2026-06-30; data as of 2026-07-10. Fictional demonstrator for a GaN-based eDrive inverter and eAxle integration. Funding: Fictional national R&D programme (example data only). [src: Meta]

1. Progress per work package

WP1 Project management and reporting

WP1 'Project management and reporting' (lead Partner A) runs from 2025-07-01 to 2027-12-31 and is active. No milestone of WP1 was due in 2026-H1. Actions due in 2026-H1: 3, of which 2 closed and 1 still open (A-024). Decision D-04-1 (MR-04, 2026-01-25): Partners report person-months every quarter. Person-months used to date: 13.6 of 14.7 planned to date (93 %); 36.0 planned in total. [src: ActionItems!12, ActionItems!13, ActionItems!24, Milestones!12, Milestones!13, WorkPackages!2, minutes/2026-01-25_MR-04.md:23]

WP2 Requirements and eAxle system architecture

WP2 'Requirements and eAxle system architecture' (lead Partner A) runs from 2025-07-01 to 2026-06-30 and is finished. Milestones due in 2026-H1: M4 done on 2026-04-17 (planned 2026-04-09). Actions due in 2026-H1: 1, of which 1 closed. Person-months used to date: 45.9 of 30.0 planned to date (153 %); 30.0 planned in total. [src: ActionItems!11, Milestones!5, WorkPackages!3]

WP3 GaN power module and gate driver

WP3 'GaN power module and gate driver' (lead Partner C) runs from 2025-09-01 to 2027-03-31 and is active. Milestones due in 2026-H1: M2 done on 2025-12-31 (planned 2026-01-11); M3 delayed (planned 2026-02-06). Decision D-04-2 (MR-04, 2026-01-25): Switching frequency target is 40 kHz. Decision D-06-1 (MR-06, 2026-05-27): A second GaN sample supplier is qualified. Person-months used to date: 37.3 of 34.7 planned to date (107 %); 64.0 planned in total. [src: Milestones!3, Milestones!4, WorkPackages!4, minutes/2026-01-25_MR-04.md:24, minutes/2026-05-27_MR-06.md:23]

WP4 Inverter control software

WP4 'Inverter control software' (lead Partner B) runs from 2025-10-01 to 2027-06-30 and is active. No milestone of WP4 was due in 2026-H1. Actions due in 2026-H1: 3, of which 3 closed. Decision D-05-1 (MR-05, 2026-03-28): Control loop runs at 20 kHz. Decision D-06-2 (MR-06, 2026-05-27): AUTOSAR is not used for the demonstrator software. Person-months used to date: 21.4 of 23.0 planned to date (93 %); 52.0 planned in total. [src: ActionItems!9, ActionItems!10, ActionItems!19, Milestones!9, Milestones!14, WorkPackages!5, minutes/2026-03-28_MR-05.md:23, minutes/2026-05-27_MR-06.md:24]

WP5 eAxle integration and thermal design

WP5 'eAxle integration and thermal design' (lead Partner B) runs from 2026-01-01 to 2027-09-30 and is active. No milestone of WP5 was due in 2026-H1. Actions due in 2026-H1: 1, of which 1 closed. Person-months used to date: 16.3 of 17.3 planned to date (94 %); 58.0 planned in total. [src: ActionItems!15, Milestones!10, Milestones!11, Milestones!15, WorkPackages!6]

WP6 Test bench validation and dissemination

WP6 'Test bench validation and dissemination' (lead Partner D) runs from 2026-04-01 to 2027-12-31 and is active. No milestone of WP6 was due in 2026-H1. Person-months used to date: 6.7 of 6.9 planned to date (97 %); 44.0 planned in total. [src: Milestones!6, Milestones!8, WorkPackages!7]

2. Milestones

ID WP Milestone Planned Actual Status Deviation Source
M1 WP2 Requirements specification released 2025-10-11 - delayed 272 d overdue Milestones!2
M2 WP3 Gate driver concept reviewed 2026-01-11 2025-12-31 done -11 d Milestones!3
M3 WP3 First GaN half-bridge samples tested 2026-02-06 - delayed 154 d overdue Milestones!4
M4 WP2 System architecture frozen 2026-04-09 2026-04-17 done +8 d Milestones!5
M5 WP6 Test bench specification released 2026-07-20 - in progress - Milestones!6
M6 WP3 Power module design freeze 2026-08-28 - planned - Milestones!7
M7 WP6 Test bench commissioned 2026-09-07 - in progress - Milestones!8
M8 WP4 Control software architecture defined 2026-11-04 - planned - Milestones!9
M9 WP5 Thermal concept reviewed 2026-11-23 - planned - Milestones!10

3. Deviations and corrective actions

Item Deviation Corrective action Source
M1 Milestone delayed, planned 2025-10-11 A-025 Agree recovery plan for M1 (due 2026-08-01) Milestones!2, ActionItems!25
M3 Milestone delayed, planned 2026-02-06 A-026 Agree recovery plan for M3 (due 2026-08-10) Milestones!4, ActionItems!26
WP2 Person-months 45.9 vs 30.0 planned to date to be explained by the WP lead WorkPackages!3

Open data-quality findings from fra lint: 8 (see the lint report). They should be resolved before the report is submitted. [src: fra lint]

4. Resource use (person-months)

WP Lead Planned total Planned to date Actual to date Actual / planned Source
WP1 Partner A 36.0 14.7 13.6 93 % WorkPackages!2
WP2 Partner A 30.0 30.0 45.9 153 % WorkPackages!3
WP3 Partner C 64.0 34.7 37.3 107 % WorkPackages!4
WP4 Partner B 52.0 23.0 21.4 93 % WorkPackages!5
WP5 Partner B 58.0 17.3 16.3 94 % WorkPackages!6
WP6 Partner D 44.0 6.9 6.7 97 % WorkPackages!7

5. Risks

ID WP Risk P I Mitigation Owner Status Source
R-01 WP2 Late changes to interface requirements 2 4 Freeze the interface with a formal change process Lead WP2 (Partner A) closed Risks!2
R-02 WP4 Target MCU resources too small for the control loop 4 3 MISSING Lead WP4 (Partner B) watching Risks!3
R-03 WP3 Switching losses higher than expected 4 4 Plan an extra layout iteration in the schedule Lead WP3 (Partner C) open Risks!4
R-04 WP6 Dynamometer slot not available in time 4 3 Book the bench slot six months ahead Lead WP6 (Partner D) open Risks!5
R-05 WP6 Measurement equipment calibration expired 4 3 Track calibration dates in the bench log Lead WP6 (Partner D) watching Risks!6

6. Plan for the next period (2026-H2)

Milestone WP Title Due Source
M5 WP6 Test bench specification released 2026-07-20 Milestones!6
M6 WP3 Power module design freeze 2026-08-28 Milestones!7
M7 WP6 Test bench commissioned 2026-09-07 Milestones!8
M8 WP4 Control software architecture defined 2026-11-04 Milestones!9
M9 WP5 Thermal concept reviewed 2026-11-23 Milestones!10

Open actions carried into 2026-H2: 11. [src: ActionItems]

Action WP Description Owner Due Source
A-006 WP3 Check dV/dt limits against the motor insulation spec Lead WP3 (Partner C) 2026-08-12 ActionItems!7
A-016 WP3 Run the double-pulse test campaign Lead WP3 (Partner C) 2026-07-16 ActionItems!16
A-017 WP6 Order the power analyser Lead WP6 (Partner D) 2026-07-11 ActionItems!17
A-018 WP6 Define the validation test matrix Lead WP6 (Partner D) 2026-08-05 ActionItems!18
A-020 WP1 Prepare input for the interim report 2026-08-21 ActionItems!20
A-021 WP1 Collect person-month figures from partners Project office (Partner A) 2026-08-09 ActionItems!21
A-022 WP6 Prepare the conference abstract Lead WP6 (Partner D) 2026-10-15 ActionItems!22
A-023 WP4 Add overcurrent shutdown test cases Lead WP4 (Partner B) 2026-08-20 ActionItems!23
A-024 WP1 Update the dissemination plan Project office (Partner A) 2026-04-27 ActionItems!24
A-025 WP2 Agree recovery plan for M1 Lead WP2 (Partner A) 2026-08-01 ActionItems!25
A-026 WP3 Agree recovery plan for M3 Lead WP3 (Partner C) 2026-08-10 ActionItems!26